Parking garage scheduled for completion in September 2019; sprinklers exempted from building codes

Construction on a parking garage in downtown Oxford has had a much later starting date than originally anticipated, and the project is now scheduled to finish in late September.

The Board of Aldermen passed four change orders regarding construction on the Oxford Parking Garage, which were needed to update the current contract with Shaw Services to reflect the new milestones.

According to plans on the Board of Aldermen’s agenda, the Oxford Parking Garage, which will be in the Oxford Square North parking lot, the date of Substantial Completion is noted as September 24, 2019.

“We’re asking to shift all those milestone dates so they are consistent with what our actual start date is,” Chief Operating Officer Bart Robinson said during the meeting.

Construction on the garage was originally slated to begin in early September 2018, but that was halted when Shaw was unable to secure a payment performance bond.

A contractor’s payment performance bond is a guarantee that a contractor or subcontractor will pay their subcontractors, material suppliers or laborers for the work and materials provided.

The parking lot was reopened for the first few Ole Miss football games of the season.

The parking garage project is also considered a year-long project, Robinson told the EAGLE in September 2018, meaning there’s a good chance the parking lot most likely won’t be open for the start of Ole Miss 2019 football season.

Board of Aldermen approve building codes, without sprinklers

After pushing back voting on updated fire and building codes due to a debate for sprinkler systems in townhomes, the Board of Aldermen finally made their decision.

Sprinkler systems will not be required in townhomes.

Aldermen Jason Bailey and Mark Huelse, who have both openly opposed requiring sprinklers in official and unofficial meetings, voiced their opinions one more time Tuesday.

Bailey explained his argument one last time to Alderman Preston Taylor, which was the current system, with the two-hour firewall and smoke detectors with battery backup were more than enough to keep families safe.

The proposed required sprinklers could cause $500,000 worth of damages if installed incorrectly.

“I feel like we have enough safety measures in place,” Bailey said.

The board unanimously approved the updated codes, with the exemption of residential townhomes having sprinklers.

The board also agreed that the fire and building departments will have 60 days to implement any changes to the approved fire and building codes.

SportsPlus

News

City leaders consider renovations to two Oxford parks

News

Plans for North Lamar’s growth could include new roundabout

Education

House buying help available for Lafayette County teachers

News

OPC hosts pilot afterschool program

Crime

Judge denies motion to seal Herrington murder case file

Crime

Abbeville man arrested after attempting to flee from deputy

Crime

Woman charged with cyberstalking

Events

Brett Young to play night before first Ole Miss home game

Lafayette County

Lafayette County property transfers

Columnists

Cofield’s Corner

Crime

MPA opposed to sealing Herrington murder case file

Healthcare

MSDH partners with Uber to provide free rides for healthcare

Events

DSU Athletics to host Manning and Rogers for A Night of Champions

Business

Baptist recognized for providing high-quality stroke care

Events

Knead Your Cure Wellness Conference: A healthy lifestyle journey

Education

NEMEPA, NE SPARC continues grant program for local teachers

Crime

New court date set for Herrington trial; Jurors will be brought in from outside county

Lafayette County

LCLEOA celebrates 25 years, honors outstanding officers, staff

Education

Students, parents reminded of cell phone use policy in local schools

Business

RKA Construction celebrates new office

Crime

Reardon sentenced to 2 years in prison for violating probation

Education

Oxford graduate to join Merchant Marines

News

Cow bones discovery temporarily halts construction project

Education

NWCC PTK alumnus lands over $14K in scholarships